At HBOWA, our engineers designed a 250kW / 215kWh energy storage system for a tower crane project in Malaysia. We designed the system to supply the construction load through PCS while coordinating utility power and battery charging.

Project Overview
| Item | Details |
|---|---|
| Project Location | Malaysia |
| Application | Tower crane power supply |
| Project Date | September 2024 |
| Energy Storage System | 250kW / 215kWh |
| Power Conversion | PCS |
| Operating Logic | Grid supply and battery charging; battery discharge through PCS when utility power is insufficient |
Customer Requirement
The construction project needed continuous AC power for the tower crane load. When utility power became insufficient, the project required battery support through PCS and automatic transfer back after utility power returned.
Our Energy Storage Solution
Our engineers configured a 250kW / 215kWh system with PCS for the tower crane application. When grid power is available, the system supplies the load and charges the battery. When utility power is insufficient, the battery supplies AC power through PCS. We designed the control logic to switch back automatically after utility power returns.